39 As part of the project to convert Hallein into a shoe care center, warehouse space was increased from 2,302 cubic meters to 5,072 cubic meters. Con struction of the above-mentioned warehouse was completed in December 2014. In the new storage rooms and all the filling areas we replaced 500 florescent lights with energy-saving LED lamps. The Production area in Hallein has also been equip- ped with Clean-In-Place (CIP) facilities for faster and water-saving cleaning of manufacturing containers. Integrated in the overall equipment concept, CIP is a cleaning system which establishes the condi- tions required to achieve consistently high product quality. Ecology